Ingwelala Shareblock

Pic of the month

See the Photo Gallery for the latest photos submitted by our members.

Regular Features

Reserve Affairs
Compiled from the latest Reserve Report - monthly
more »

From the Board
Communications from the Board - quarterly
- Updated 14/12/2016

more »

Conservation
Compiled from the latest Reserve Report - monthly
more »

Building Projects
Building at Ingwelala that might affect your visit - monthly
more »

Sightings
Recorded sightings and members' stories - monthly
more »
 
Gate Letter
Download this month's Gate Letter
more »

Weather

Rainfall: February 2017:
1983 - 2017 49.2mm
   
Temps:
1992 - 2017
Max: 38°C
Min: 19°C
   
7/14 Day forecast - Ingwelala

Project: Vuka Ingwe

The design is x4 identical rooms consisting of bedroom, shower and toilet, kitchenette and veranda. A plaster and paint interior with face brick exterior. Non thatch.

The purpose of the build is to upgrade staff accommodation with the long term objective of each staff member having his/her own private accommodation and not shared accommodation. This build will ensure that x8 staff immediately benefit from not having to share accommodation.

18/08/2014

The (phase one) project is completed and accommodation ready for occupation



15/07/2014

June's progress update on the accommodation unit being built at Vuka Ingwe.

     


17/06/2014

May's progress update on the accommodation unit being built at Vuka Ingwe.>

     


17/05/2014

The following pictures provide a progress update on the accommodation unit being built at Vuka Ingwe.


15/04/2014

The following pictures provide a progress update on the accommodation unit being built at Vuka Ingwe.


Marking build site and trenching foundations
 
Casting the foundations

Laying first course foundation bricks
 
Final preparation before casting floor slab